Koeberg Unit 1 return to service extended due to additional steam generator maintenance; passes structural integrity tests – no increased risk of loadshedding.

Africa Biz Watch by Africa Biz Watch
July 15, 2025
Loadshedding remains suspended for 282 days with year-on-year diesel savings of R16.52 billion achieved
Share on FacebookShare on Twitter

Tuesday, 15 July 2025: Eskom today shared an update on the planned maintenance of Unit 1 at the Koeberg Nuclear Power Station in Cape Town, which is currently offline for the second phase of its long-term operation maintenance programme. Initially expected to return to service by July 2025, the unit is now scheduled to be back online by end of August 2025. This revised timeline underscores Eskom’s commitment to conducting thorough inspections and maintaining the highest quality standards to ensure the ongoing safe and reliable performance of South Africa’s only nuclear power station.

During scheduled detailed eddy current inspections — a non-destructive testing method used to detect cracks, corrosion, or wear in the metal tubes of steam generators — defects were identified on four tubes among several thousand tubes inspected, across two of the newly installed generators.

Eskom immediately carried out an advanced automated process to address the four tube defects, supported by specialised international teams working alongside local experts. These critical repairs have now been successfully completed to uphold the highest safety and quality standards.

Importantly, the major maintenance activities, which included the legally required 10-year Integrated Leak Rate Test (ILRT), where the reactor building was pressurised over 72 hours and its leak rate and structural integrity were monitored — were successfully completed. The ILRT confirmed the robustness and leak-tightness of Unit 1’s containment structure, further reinforcing its safety in line with international standards.

“Our top priority is always the safety of our employees, the public and the environment. Carrying out these additional inspections and repairs to world-class standards, we are investing in the long-term reliability of Koeberg and South Africa’s energy future,” said Bheki Nxumalo, Eskom’s Group Executive for Generation.

“The planned maintenance underway on Unit 1 will help deliver decades of affordable, low-carbon baseload power, demonstrating how nuclear energy can support both economic growth and environmental sustainability. Through our commitment to high-quality maintenance and the expertise of the Koeberg team demonstrating exceptional skills, we are ensuring nuclear power remains a vital part of the country’s energy mix,” concluded Nxumalo.

Major generation milestones in 2025

In parallel, Eskom has also made significant progress on other generation projects this year, with two of them already adding 1 600MW to the grid.

  • On 23 March 2025, the new 800MW Kusile Unit 6 was successfully synchronised to the national grid and will be on commercial operation by September 2025.
  • From February 2025 to the end of May 2025, the 800MW Kusile Units 1, 2 and 3 were safely reconnected to the repaired west stack and are now operating with their flue gas desulphurisation (FGD) systems. This follows the temporary authorisation granted by the Department of Forestry, Fisheries and the Environment (DFFE) to operate without the FGD system under strict conditions until 31 March 2025, after the 2022 structural failure.
  • On 6 July 2025, the 800MW Medupi Unit 4, which had been on a long-term outage since August 2021, was returned to service.

These milestones highlight Eskom’s commitment to improving generation capacity and securing electricity supply.

No added risk of loadshedding

The revised return date for Koeberg Unit 1 will not increase the risk of loadshedding. The Winter Outlook released on 5 May 2025, which covers the period until 31 August 2025, remains valid. Importantly, the planned return of 2 500MW this winter does not rely on Unit 1.

The outlook shows that loadshedding will not be required if unplanned outages remain below 13 000MW. Even if outages rise to 15 000MW, loadshedding would be limited to a maximum of 21 days over the 153-day winter period, capped at Stage 2. Since 15 May 2025, no loadshedding has been implemented, and only 26 hours of loadshedding have been recorded for the financial year to date (1 April to 10 July 2025).

Once all maintenance work is complete, Unit 1’s reactor core will be refuelled, tested and synchronised back to the national grid.

RelatedPosts

Why higher tariffs on Canadian lumber may not be enough to stimulate long-term investments in US forestry

Labour inspections yield positive results

SAPS trainees complete SASSETA training programme

National Executive is not above the law – President Ramaphosa

To protect supply, planned outages at Koeberg are carefully staggered every 16 to 18 months so that both units are never offline at the same time. Together, Koeberg Units 1 and 2 provide around 1 860MW — approximately 5% of the country’s electricity needs.

Unit 2 remains fully operational, generating up to 946MW, with a year-to-date Energy Availability Factor (EAF) of 99.38% as of the end of June 2025.

The national power system remains stable, with a month-to-date EAF of 62%. As the winter season continues, Eskom encourages all customers to adopt energy-efficient practices.

ENDS

Source link

Related Posts

Why higher tariffs on Canadian lumber may not be enough to stimulate long-term investments in US forestry
News

Why higher tariffs on Canadian lumber may not be enough to stimulate long-term investments in US forestry

October 15, 2025
Labour inspections yield positive results
Government

Labour inspections yield positive results

October 15, 2025
SAPS trainees complete SASSETA training programme
Government

SAPS trainees complete SASSETA training programme

October 15, 2025
National Executive is not above the law – President Ramaphosa
News

National Executive is not above the law – President Ramaphosa

October 15, 2025
Government shutdown hasn’t left consumers glum about the economy – for now, at least
News

Government shutdown hasn’t left US consumers glum about the economy – for now, at least

October 15, 2025
Starbucks wants you to stay awhile – but shuttering its mobile-only pickup locations could be a risky move
News

Starbucks wants you to stay awhile – but shuttering its mobile-only pickup locations could be a risky move

October 14, 2025
In defense of ‘surveillance pricing’: Why personalized prices could be an unexpected force for equity
News

In defense of ‘surveillance pricing’: Why personalized prices could be an unexpected force for equity

October 14, 2025
New student loan limits could change who gets to become a professor, doctor or lawyer
News

New student loan limits could change who gets to become a professor, doctor or lawyer

October 14, 2025
Next Post
Datumstruct Enhances Singapore Experience Centre for Command Centre Technology

Datumstruct Enhances Singapore Experience Centre for Command Centre Technology

VinFast Advances Ecosystem Strategy in Philippines’ EV Catch-Up

VinFast Advances Ecosystem Strategy in Philippines’ EV Catch-Up

VinFast to introduce new model in Indonesia upon return to GIIAS 2025

VinFast to introduce new model in Indonesia upon return to GIIAS 2025

2026 FIFA World Cup expansion will have a big climate footprint, with matches from Mexico to Canada – here’s what fans can do

When big sports events like FIFA World Cup expand, their climate footprint expands too

Loss before tax for the 2024 financial year improves by R9 billion to R25.5 billion; NTCSA separation triggers once-off accounting adjustment leading to loss after tax of R55 billion; profit forecast for the 2025 financial year due to improved performance.

Leadership appointment at Eskom Distribution

Recommended.

Eskom issues alert of high risk of loadshedding following over ten months of uninterrupted power supply – Summer Outlook remains unchanged.

Loadshedding was suspended at 05:00 after it was implemented following the loss of five units prior to and during Wednesday’s evening peak – ongoing high levels of planned maintenance continue until early April.

March 20, 2025
Amur Gas Chemical Complex 75% Complete, Reports SIBUR

SIBUR Begins Installation of Polypropylene Production Line at Amur GСC

July 30, 2025

Trending.

No Content Available

Publish News, Boost Your PR, SEO, and Business Exposure with SagloMedia's Dedicated Brand Sections

Discover More

News Publications

  • EBNewsDaily
  • South African Business News
  • BetsBulletin SA
  • PressNest
  • EconoNews
  • AfricaBiz Watch

Listing Directories

  • MySouthy
  • BizFinder Directory
  • ListBig
  • SA Companies
  • OutingPlace
  • Rental Kings

Quick Links

  • Home
  • Advertise
  • Publications
  • Company News
  • Privacy Policy
  • Copyright & Takedowns

SagloMedia

  • About us
  • Careers
  • Student Program
  • RSS Feeds
  • Press Code
  • Contact Us

Get In Touch

  • info@saglomedia.co.za
  • Tel: +27 10 880 3950
  • WhatsApp: +27 10 880 3950
  • Johannesburg, South Africa
  • SagloMedia
  • www.saglomedia.co.za
Copyright © 2025 | SagloMedia

Saglohost Web Hosting | Web Hosting South Africa | Web Design Johannesburg | Web Design South Africa | Saglotech | Web Design Company | SEO Company South Africa | SEO Company Johannesburg